Nobody can honestly tell you what your house will cost from a square-metre rate, and that includes me. We’ve built on a clifftop dune at Forresters Beach, rock full of clay at Killcare, a landslide-prone peak at Avoca Beach and a riverfront block at Mooney Mooney you can’t get a truck to. The same size house costs a very different amount on each.
Building is getting more expensive everywhere: residential construction costs rose 3.2 per cent in the year to September 2026 (Cotality). A good builder spends your budget on the house instead of on surprises. This is why choosing the right builder is so important.
The short answer
- Published rates for architect-designed homes sit between about $4,645 and $8,318 a square metre before GST (BMT, 2026). Where you sit in that range depends on your block.
- On the Coast, you pay the most extra for the ground, access and your bushfire rating.
- BAL FZ windows cost around $3,500 a square metre to supply, against $800 to $1,200 for normal windows. Installation is extra.
- Hold 10 to 15 per cent of the contract as contingency.
- Get a builder on the block before the drawings are finished. I start every client with the Dream Home Brief.

Published building costs per square metre
These are other people’s figures, all for the house itself, and the range is wide.
| Source | Figure | What it covers |
|---|---|---|
| ABS, 2024-25 | $565,749 average | Every new house in NSW, project homes included. GST in, land out. About $2,400 a m² |
| ABS approvals, 2025-26 | About $500,000 average | 861 new houses approved in the Central Coast council area |
| Central Coast Council, 2025 | $3,690 to $5,740 a m² | Council’s own guide: high standard to prestige finish, ex GST |
| Rider Levett Bucknall, 2026 | $2,500 to $7,600 a m² | Custom-built houses, Sydney rates, ex GST, before site works and fees |
| BMT, 2026 | $4,645 to $8,318 a m² | Architecturally designed homes, Sydney rates, ex GST, garages and verandahs counted |
Before you compare two quotes, check three things:
- Area – house only, or garage, decks and alfresco too?
- GST – in or out?
- Site costs – excavation, piers, retaining and services inside the rate, or extra?
Six things that make a build cost more
When someone asks me what their house will cost, site conditions and bushfire requirements come to mind first. On a flat block with good ground, everything can be brought in, brought out and installed a lot quicker.

1. The ground
You don’t know what’s under a block until you dig. At Killcare the whole site is on rock, and you’d think that means good foundations. It turned out to be poor rock, with clay bands and ironstone all through it.
Trenches you’d normally dig with an excavator or a shovel needed a wet saw or a rock saw. The water turned the site to mud, and a jackhammer stops working the moment the rock turns to clay. Those jobs took five times as long.
At Oceano in Copacabana it was boulders 1.5 metres down. The drill rig kept hitting them, so we jackhammered the deep footings by hand.


2. Slope and access
Every level you cut into a hill needs retaining, drainage and engineering, and every delivery costs more to get in. On the steep Avoca Beach site we’re building now, in an area with a history of landslides, the landscape had to be resolved before we could start. At Mooney Mooney, materials came in by a 70 metre carry from the street.
At Killcare there’s no parking, every lift needs a crane, and power lines cross the driveway. SafeWork NSW sets a 3 metre minimum distance for a crane near low-voltage lines (code of practice, May 2026). We have to set the crane up further back with a longer reach, and that costs more. There’s no phone reception on that site either, so everything happens by email, WhatsApp or FaceTime. Some people don’t have easy access to those.
There’s more on geotech reports and foundations in our guide to building on a sloping block.


3. Your bushfire rating
BAL FZ (flame zone) is by far the biggest cost add. The extra cost is in the windows, decks and cladding.
| BAL 40 | BAL FZ | |
|---|---|---|
| Windows | Still cost effective | Around $3,500 a m² supply only, against $800 to $1,200 for normal windows. Installation is extra. Shutters are a cheaper alternative |
| Decks | No timber: a tiled, enclosed waterproof deck or a tiled concrete deck, both significantly more | Same |
| Cladding | Limited choice, not usually a cost driver | Same |
Window rates are supply only, from our current jobs, November 2026, and every job is priced on its own glazing schedule. Australian Standard AS 3959 sets the levels, from BAL-LOW to BAL FZ, and the RFS applies them in NSW through Planning for Bushfire Protection 2019. A home at BAL 40 or BAL FZ needs a full Development Application.
Some owners add a bushfire sprinkler system on top, from about $40,000. Our Killcare home is BAL 40 and the owners chose one. More on the build side in our BAL FZ guide.

4. Wind, salt and water
Exposed coastal sites need higher wind ratings under AS 4055: more bracing, stronger fixings and higher-rated windows. Our Killcare home is designed for N4 wind. On the clifftop at Forresters Beach, salt crusts the glass within hours of a southerly, and we built in a window washdown system to deal with it.
Most of our jobs are on elevated blocks, so we rarely deal with flooding. Under the Central Coast DCP 2022, habitable floors on flood-affected land must sit at the one-in-100-year flood level plus 500 mm. Council can issue a flood certificate with the level for your lot.
5. Design and finishes
Flush floor transitions, curves, high-end joinery and the material palette cost more than most clients expect. Some people don’t notice the little things. We specialise in them, and every one takes extra hours on site.
You save the most by going through the design with your builder before it’s locked. At Killcare the plans called for off-form concrete and rendered blockwork. I suggested we leave the block raw to tie in with the concrete, and we saved the render costs.

6. What’s behind the walls
The real quality of a home lies behind the walls. How it operates mechanically, electrically and passively (heating, ventilation, insulation, how it holds warmth in winter) all adds cost, and none of it shows in a render.
Your side of it
Got a block in mind?
Section 2 of the Dream Home Brief asks about the zoning and building constraints you already know about (bushfire, flood, heritage, easements), and section 5 asks where the money sits.
Start the Dream Home BriefWhy costs go up during the build
Every custom home starts with some decisions still open. In my estimates I make an allowance for them: a prime cost item (PC) for things like tapware, a provisional sum (PS) for work like rock excavation. On site I explain it like this: a PC item is a thing, a PS is a job. There’s more on how they’re adjusted in our lump sum contract guide.
Changes mid-build cost clients the most: late selections, ground conditions nobody could see, and one change after another.
Most of it can be avoided with more time in pre-construction. With renders of the finished home and the interiors, you can see what you’re getting and make decisions on paper instead of on site. For what you can’t plan for, hold 10 to 15 per cent of the contract sum as contingency, and at least 15 per cent on a slope, a waterfront block or a design still changing.
The costs outside the build price
- Design and engineering – architect or building designer, engineers, surveyor. Good Architect puts architect and consultant fees at 5 to 15 per cent of the build cost (source).
- Reports – geotech, and a bushfire assessment if you back onto bush.
- Approvals – the statutory DA fee on a $1.5 million house is about $4,345 (2026-27 scale), plus the certifier. A single house is exempt from council’s section 7.12 levy (contributions).
- BASIX – a new NSW house needs a 7-star NatHERS rating (Planning Portal).
- Services – Central Coast Council supplies water and sewer and sets its own developer charges. Power is Ausgrid.
- Levies and insurance – the Long Service Levy is 0.25 per cent of work over $250,000 (NSW Government), and your builder must hold home building compensation cover on any contract over $20,000 (Service NSW).
- Outside the walls – driveway, landscaping, fencing, pool, and demolition if there’s an old house.
- Time – the longer approvals and the build take, the longer you’re carrying the land and the loan.
Choose your builder before the drawings are finished
The most expensive way to find out what your home costs is to finish the drawings, get them approved and then send them out to price. If the price is too high, you pay to redesign.
When I come out to a site, I’ll tell you whether your budget and your drawings line up, or how far apart they are. I’ll tell you what the site is going to do to the cost. Slope, rock shelf, coastal wind loading, the DA. More on timing in how to choose a builder, and the money questions are in my 21 questions to ask a builder.

Got a block on the Coast? Start with the Dream Home Brief, or book a free site visit and I’ll walk it with you.